Open Web Girder Bridge Launching
120 m
Maximum clear launch span
2,800 t
Peak girder launching weight
±2 mm
Laser pier seating tolerance
Zero
Track closure incidents recorded
Four Stages of Precision Launching
Abutment Pre-Assembly
Launching Nose Fitting
Synchronized Jacking Push
Final Lowering and Seating
Truss bays are fitted and torque-inspected on stabilized ground-level launching beds, establishing calculated upward cambers for dynamic deflection control.
A lightweight tapered steel nose attaches to the lead truss segment to bridge the gap and land smoothly onto pier rollers before peak cantilever stress.
Computerized horizontal hydraulic strand jacks and PTFE sliding pads advance the continuous superstructure smoothly at calibrated low speeds.
Once target longitudinal alignment is certified by laser metrology, synchronized vertical jacks lower the truss onto permanent elastomeric bearings.